Water Sanitation and Hygiene - Kalalu

Visit by Martin Kibuuka on 2022-01-24

Report ID
15517
Created by
Martin Kibuuka
Created date
2022-01-25 08:08:28 UTC
Modified by
Lorna Katagara
Modified date
2022-01-27 11:40:13 UTC
Trip Time
10:00-18:46 (8 h 46 m)
Village Time
12:06-15:30 (3 h 24 m)
Travel Time
5 h 22 m

Household visits

Which Survey
none 
Number Of Households
Visits Purpose
Borehole installation program. 
Staff Attendees
Martin Kibuuka 
Government Attendees
LC1,VHT,Other 
Notes
Martin was in Kalalu, his intention was to supervise the new borehole installation in that village. Good enough, when the installation program talk place, they had a great number of people around the borehole site. Every one was so happy, especially the women, because In Busoga region, women are the most people who always suffer, to fetch water for their husbands and their children and to walk for long distances. So Martin was encouraging encouraging the residents, to continue caring for their new borehole. Because in that new borehole kibo put new cylinder, 8pipes, 8rods and the Head assembly. At last Martin told the village leaders, to mobilize the residents to collect the bricks, stones and the sand, for the borehole wall face. 
Next Visit
2022-01-31 - Purpose: Borehole wall fence construction.
Program Success
The work of installation was done and the village was so happy.
Program Critical Needs
They need more encouragement about maintaining and caring for their new borehole.
Program Ownership
They worked so hard on their new home facilities, on their own without force.
Other Program Observations
Non
Program Expected Of Village
To prepare themselves for the borehole wall face construction.
Program Staff Preparations Next Visit
To call the village leaders and hear weather the residents have collected the bricks, sand and stones, for the borehole wall fence construction.
 

Report Photos

25225 That’s how the community members and Draco workers, was busy on the borehole installation.
25228 That’s how the Draco workers was testing the new cylinder, to select the best one, to put inside the new borehole.
25231 That’s how the Draco workers was fixing the new pipes inside the new borehole.