Water Sanitation and Hygiene - Nabituluntu - Namutumba
Visit by David Balimunsi on 2017-12-08
- Report ID
- 496
- Created by
- David Balimunsi
- Created date
- 2017-12-08 12:30:32 UTC
- Modified by
- Ben West
- Modified date
- 2018-02-09 21:11:54 UTC
- Trip Time
- 09:29-17:37 (8 h 8 m)
- Village Time
- 12:30-15:35 (3 h 5 m)
- Travel Time
- 5 h 3 m
Current State
- Participation Rating
- 2
- Success
- They have taken good care of their borehole by having 250000 shillings as their borehole account money and strong fence too
- Village Critical Needs
- They need fire saving Steve’s
- Village Action Steps
- It is to continue working and improving on the facilities that are not meeting the reuired high good standards of hygiene and sanitation
- Staff Action Steps
- It is to encourage the entire residents of the area taking good care of the borehole as well as working and reviving on the hygiene facilities that were not meeting the required sanitation standatds
- CLTS Progress
-
- Sanitation Hygiene Committee
- yes
- Water Users Committee
- yes
- Other Class Notes
-
- Community Ownership
- yes
- Ownership Story
- Facilities like dish racks,shower areas ,rubbish pits,houses and kitchens have been maintained and kept clean .and the borehole good status has maintained .
- Three Stone Fires
- yes
- Access to Clean Water
- yes
- Open Defecation
- no
- Water Access Explain
-
- Prevent Ownership
- None
- Allow Ownership
- The cooperation and mobilization between the committee members and the other residents of nabituluntu is so good.
- Village Notes
- Because of the unity brought by Kibo to nabituluntu village apparently they can work together for example mr tilibagenyi the chairman Lc1 of upper nabituluntu can now lead meetings in the lower section were he used not before.For that reason Kibo staff were so happy seeing that the two villages could sit and work together in different developmental aspects,they thanked the chairman mr Samuel Galevu from the lower section and mr tulibanyi of the upper section for encouraging all the two sections coming together and working together. The borehole which Kibo repaired in the upper section was kept so good with a strong fence and even some member from the lower section were seen getting water from the upper section which never used to happen before.David asked the chairman mr tulibanyi from upper section how much-money they were having on their account for the borehole he took David to the treasures home they showed him the 220000shillings cash as their borehole account balance.kibo staff moved in fifty homes carrying out the evaluation process ,but in the different homes they were working into they kept on encouraging the residents they came across working and improving on some facilities which were not meeting the required good standards . The members were advised continuing working together in all the different village programs not forgetting having monthly borehole contributions meetings aimed at accessing the status of their borehole and the hygiene and sanitation of the different homes. They meet two V.ht,s during the process of evaluation and reminded them of their roles and responsibilities encouraging the other members about improving their sanitation standards.In general from the evaluation made by the Kibo’s staff the members have maintained their sanitation facilities according to the required standards apart from one facility the hand washing facility which was a challenge in most homes.
- Next Visit
- - Purpose:
- Program Success
- Program Critical Needs
- Program Ownership
- Other Program Observations
- Program Expected Of Village
-
- Program Staff Preparations Next Visit