Trip Time
10:36-17:54 (7 h 18 m)
Village Time
12:56-15:31 (2 h 35 m)
Travel Time
4 h 43 m

Water Community Meeting

Meeting Topic
contribution 
How Many Men Attended
13 
How Many Women Attended
Staff Attendees
Walyomu Alex 
Government Attendess
LC1,LC2,VHT 
Visitor Attendees
 
Total Attendance
22 
Look Up
 
Notes
The meeting in Igerera B was about to engage the village to work together more and complete the remaining steps before the borehole commissioning. The village still has more steps to meet before the borehole is used. The two boreholes in the village need the new wall fences as mandatory before the borehole can start to be used. However the village has lately been struggling because they have not yet got all the materials required for the two wall fences. The discussion was about how to involve all the people and make sure they get all the construction materials and have both fences worked upon. The village agreed together that they would lock all the available water sources in the village to succeed getting money from all the people in the village. Also the village LC chairman will work closely with the two water committees for both wells home to home collecting contributions from every household and promised to collect the required money in a week. On the other hand, some of the people had lost some facilities to rains and Alex saw some people constructing new facilities replacing collapsed facilities including the chairman of the water user committee of the new well who was met building a new pit latrine structure after the old one had been washed away by the rains. Alex will continue to go back and follow up on this to make sure the wall fences are constructed, borehole account active before the village can start to use water from the new well. 
Next Visit
2019-12-04 - Purpose: Follow up on the borehole contributions required
Program Success
The new borehole slab has dried well and ready for pumping. Also the people of the village that had lost some of the facilities due to the current heavy rains.
Program Critical Needs
Program Ownership
Some new facilities were seen replacing those that have been damaged by the recent rains of which some collapsed
Other Program Observations
Program Expected Of Village
Convene another meeting and come up with a way forward to meet the remaining steps before the village can start to use the new well.
Program Staff Preparations Next Visit
Call the water user committee to find out if they have managed to get all the materials needed to construct the wall fences around the two wells in the village
 

Report Photos

9770 The new borehole in Igerera B
9773 The new borehole slab
9776 Alex in a meeting with the water user committee and some of the community members about how to work together as a village to complete the remaining steps before the new borehole commissioning. Also together had a discussion on how to get the money and materials to build two wall fences around the two boreholes.